Swiss Chalet, Glen Helen

Restoring an iconic Isle of Man landmark after fire damage

Completion date

August 2024

Location

Glen Helen, Isle of Man
Restored Swiss Chalet at Glen Helen behind the blue ornamental fountain
Swiss Chalet at Glen Helen set in woodland after restoration
Restored Swiss Chalet at Glen Helen after fire reinstatement
Fire-damaged Swiss Chalet at Glen Helen with scaffold and temporary protection
Fire-damaged gable and balcony of the Swiss Chalet at Glen Helen before restoration
Fire-damaged roof void of the Swiss Chalet at Glen Helen under a temporary roof
New roof structure inside the Swiss Chalet at Glen Helen under a temporary roof
New roof timbers inside the Swiss Chalet at Glen Helen during reinstatement
New timber cladding and dormer on the Swiss Chalet at Glen Helen during restoration
Gable of the Swiss Chalet at Glen Helen during reinstatement, with new timber cladding
No items found.

The Challenge

The Swiss Chalet at Glen Helen is a prominent public landmark on the Isle of Man. Following a fire that compromised a significant section of the roof and internal structure, DEFA required the building returned to its original appearance, with performance upgraded and long-term durability secured for a structure exposed to harsh conditions in a remote location.

‍

Exposed through winter

Large sections of the roof structure were open following the fire, leaving the building at high risk of weather ingress and further structural deterioration. The programme had to be maintained through winter without letting the elements undo the work.

No drawings to work from

Original architectural details had to be replicated without full design information available, including designing and reconstructing a dormer window from scratch to match the existing, where no original drawings could be found.

A public landmark

As a prominent public-facing building owned by DEFA, the chalet demanded a high visual standard throughout, including sourcing and integrating matching roof tiles and the careful salvage and reinstatement of existing materials.

Note
Update the layout351_vertical-text-styling class names in HTML if you change this component.

Our Approach

A temporary-works-led restoration: weather-tight first, then rebuild with care.

01

Weather-tight first

Structural integrity

Weather-tight first

A bespoke temporary roof enclosure was designed and installed so works could progress safely through winter in a fully protected environment, not patched up to wait out the season.

New roof timbers inside the Swiss Chalet at Glen Helen during reinstatement
02

Repair, not replace

Safety systems

Repair, not replace

Selective demolition and structural repair replaced fire-damaged rafters, purlins and roof elements while retaining and protecting everything that remained sound.

Gable of the Swiss Chalet at Glen Helen during reinstatement, with new timber cladding
03

Tiles matched

Accessibility standards

Tiles matched

Approximately 50% of the existing roof tiles were carefully salvaged and reinstated, with replacement tiles sourced off-island to give a close aesthetic match for the remaining coverage.

New timber cladding and dormer on the Swiss Chalet at Glen Helen during restoration
04

Details rebuilt

Transparent documentation

Details rebuilt

Bespoke joinery restored the timber windows, shutters, balcony balustrade and fascia detailing, and a new dormer window was designed and built from scratch to match the existing, with no original drawings to work from.

Gable of the Swiss Chalet at Glen Helen during reinstatement, with new timber cladding

The Result

The Swiss Chalet has been returned to full operational condition for DEFA and the visiting public, with its original architectural character restored, its long-term durability improved, and new and existing materials seamlessly integrated. Delivered within the planned programme window despite working through winter.

Final account

£225k

delivered to the agreed scope for DEFA, within the planned programme window, despite winter working on a fire-damaged, partially exposed structure

Tiles salvaged

~50%

of the existing roof tiles carefully salvaged and reinstated to maintain visual continuity, with replacement tiles sourced off-island for a close aesthetic match

Rebuilt from scratch

1

dormer window designed and reconstructed to match the existing with no original drawings to work from, alongside bespoke timber windows, shutters, balustrade and fascia detailing

Ready to build?

Tell us what you're planning and we'll give you an honest view of cost, programme and process.